Time wasn’t on their side

Nunavut regulator opposes uranium mine

A lack of a start date, not health or environmental concerns, result in recommendation to reject the proposed Kiggavik facility
Oil & Minerals
Areva-derci (Photo: Areva)

Share this article

Facebook Google Twitter Mail

iAbout Press releases

As part of our continuing efforts to bring you as much information about our region as possible we offer readers a press release service that allows private firms, public agencies, non-governmental organisations and other groups to submit relevant press releases on our website.

All press releases in this section are published in their full length and have not been edited.

If you have a press release or other announcement you would like to have published, please send it to [email protected].

We reserve the right to reject press releases we deem irrelevant or inappropriate. 

All material submitted to The Arctic Journal, including pictures and videos, will be assumed to be available for publication by The Arctic Journal and its related entities.

Anti-uranium mining voices in Nunavut are claiming an uncertain victory after the NIRB, a territorial authority, recommended to the federal government that the hotly contested Kiggavik mining project not be approved.

The decision, issued on May 9, comes after a review process that has taken six years and involved input from a slew of land-use groups, environmental protection organisations and government agencies of varying levels.

The C$2.1 billion ($1.75 billion) project is being eyed for a site located some 80km west of the Nunavut community of Baker Lake and would consist of two mine sites operating both open-pit and underground mines. According to Areva, the French firm that has been seeking to establish the mines since 2009, those facilities would have created 400 jobs, many of which it said would be filled by people living in the territory.

SEE RELATED: Asking the right questions about uranium

This is not the first time the people of Baker Lake have been asked their opinion about uranium mining. In 1990, the idea of opening a mine on the same site was soundly rejected in a local referendum. Attitudes have changed since then, however, and some in the community are ready for the development the mine will bring. Neither is the uranium the pariah it once was in the eyes of territorial and indigenous leaders.

Still, opponents warn that there is more at stake than the mines’ economic benefit. The operation, they say, would be disruptive to wildlife, particularly the caribou that roam the area. Others are concerned about the dust that mining and blasting would kick up and, which, carried on winter winds that can reach 80km per hour, had the potential to be spread over a far wider area than the company estimated.

Likewise, Areva’s plans to partially drain a lake, and its proposal to fly yellow cake, a powered form the partially refined uranium ore, out of the area on cargo planes, fail to sit well with people living in the area.

A broader concern among opponents is that once Areva establishes a mining infrastructure in the area, it will be easier, and cheaper, for other firms to follow.

SEE RELATED: Mary river facing hurdles on both sides of Baffin Bay

In the end, the NIRB, in principle, sided with Areva when it came to the question of whether the operations would be a health or environmental hazard. It also felt that Canada’s nuclear regulator could ensure that the project could be conducted safely.

On certain issues, such as the spread of dust, it did note that there was a difference of opinion between Areva’s calculations and the concern of local groups, which the board considered to be valid. But, it felt that better monitoring would be a sufficient compromise.

Even with its positive outlook, the board moved to recommend that the application be rejected anyway. The reason was that Areva chose not state when the project would get underway. This was a problem, opponents said, because it was likely conditions on the ground would change before mining began, thus making the company’s assessment of the environmental worthless.

Areva, for its part, defended the lacking start date on the grounds that the current market price for uranium is too low to make the operation profitable. No-one one providing testimony during the final hearing in March could say with much accuracy when operations might begin for certain, though some groups suggested it could take as long as 20 years.

SEE RELATED: A natural-born partner

Issuing a licence not likely to be made use of for so long, hunters argued, would make a mockery of the approval process.

"We do not want this proposal approved but still hanging over our heads for decades to come, not knowing what the future of our community will be," the Baker Lake Hunters and Trappers Organization, told the board in its testimony. The NIRB agreed.

And while the NIRB did give a passing mark to Areva’s overall application, stating in its final decision that even though Kiggavik should not be approved “at this time, this does not mean that this project should not proceed at any time”, it suggested that the company could strengthen its bid in a number of areas, should it apply again.

For example, the firm had not established terms in Inuktitut, the local language, that described uranium mining and its potential impacts. The board also said better information about caribou population development would be helpful. Finally, it hoped to see better training programmes that would afford Nunavut residents a better opportunity to work at the mine.

SEE RELATED: Editor’s Briefing | Another one bites the ore

The decision is now in the hands of the Aboriginal Affairs and Northern Development Canada, a federal ministry. Officials there can either accept the NIRB’s recommendation or reject it on if they deem the project to be in the national or regional interest.

If the AANDC decides the project should go ahead despite the recommendation, it will ask the NIRB whether any conditions should be placed on the approval.

Areva, which expressed “disappointment” about the ruling, says it will read the report closely before deciding about a further course of action.

Additional reporting provided by Brian Pehora.